A managed London extension build. From our drawings, or from yours.
A managed London extension build. From our drawings, or from yours.
Our Build Phase runs a single contract with you, a dedicated Build Manager on site, ten-stage payment in arrears, and a three-year structural warranty. A typical London single-storey extension build runs twelve to twenty weeks on site. We build from any architect's drawings — ours, yours, or a third party's.
Carry on to the Build Phase. Same team, single contract, no re-tender.
Book a build consultationSend us the drawings. We'll quote a fixed-price build inside ten working days.
Get a build quote£2,800–£5,500+ per m2 for an architect-designed extension on a London Victorian or Edwardian terrace (May 2026 figures).
that is £56,000–£110,000 build cost, before kitchen fit-out.
brick-matched to existing Victorian or Edwardian stock, bi-fold or sliding doors, integrated lighting, mid-range kitchen fit-out, full Building Regs compliance.
architectural glazing, underfloor heating, specialist tiling, bespoke joinery.
the borough (West London typically +10–15% on East), conservation status, ground conditions, access constraints (Victorian terraces with no side access add cost), the spec of the kitchen.
[Postcode-level averages — TBC with Dan from BuildTeam project data]
Site setup & strip out
1 week
Foundations are dug and poured
2 weeks
New cavity walls
1 week
Structural steels installed
1–2 weeks
Roof construction
2 weeks
Drainage and sub floor
1 week
Insulated screed floor
2 weeks
Timber partition and plaster skimming
2 weeks
Practical Completion
1 week
Snagging
1 week
The contract is fixed-price against an agreed specification. Variations only come from you asking for a change in scope, or from genuine site discoveries (rot, ground conditions, drains) that cannot be identified without invasive works. A contingency of around 10% is standard practice for any London extension and we recommend building that into your budget at the outset.
As part of our service, we will replace the Principal Contractor with another from our vetted pool in the unlikely event they can't complete the project after they've started.
The Build Manager owns the Building Control diary from day one and books inspections in advance of each stage. Local authority Building Control fees for a typical London extension are generally between £900–£1,500. Where instructed to do so, the Build Manager will liaise with Building Control and the Principal Contractor to facilitate the sign off process upon completion.
On most single-storey ground floor extensions you can stay in the house — the kitchen comes out during the strip-out phase and we can set up a temporary one for the duration of the works. For loft conversions, most clients remain at the property for the duration of the works – and for full-house refurbishments they tend to move out for some or all of the works. We produce a project programme at the outset which will indicate the most disruptive elements of the schedule.
Weekly site visits. Dedicated point of contact. Owns contract administration and payment certifications.
Build Director
Build Manager
Build Manager
Build Manager
A single-storey ground floor extension project costs roughly £80,000 – £150,000 inclusive of VAT in 2026.
The construction of the shell & core takes approximately 14-16 weeks. We recommend allowing an additional 2-4 weeks for the finishing schedule to be undertaken.
Yes, we can build from another architect's drawing set. We will also require structural engineering calculations and building regulation drawings and can produce these via our in-house design team if you require them.
Working with a design and build company means you have a single point of contact from start to finish. It also means the tender process happens more quickly — or dispensed with entirely if you ask us to fix the build costs upfront before the design phase gets underway. If you appoint a separate Architect, you will need to pay them to tender the project to contractors or undertake this part of the process yourselves.
The structural warranty is for a period of 3 years following completion, during which Build Team will guarantee the works against major structural defects.
Upon completion of core milestones identified within the project planner, your Build Manager within 48 hours of notification from the contractor will raise in part or in full the payment certification for that stage. Payment to the Principal Contractor is due upon receipt of this certification.
Ahead of signing a build contract with us our Build Director will review your Architect's drawings to make sure they are buildable. If there is something incorrect or missing from the drawing package — we will identify this to you so that you can go back to your Architect to make the required amendment ahead of starting the build.
A Party Wall Notice will need to be served before you commence works if you are intending to excavate foundations within 3m of your neighbours' property.
Building Control will need to be appointed prior to works commencing on site which takes up to 10 days; they will inspect the construction drawings and make regular planned site visits and issue the final build certificate. You can appoint Building Control yourself, or you can appoint Build Team to administer this process on your behalf for an additional fee.